FABRICATION PIPELINE
Four phases, each with a clock and failure modes worth knowing.
1
Schematic capture 2–4 days
- Part selection & sourcing check before layout.
- ERC + design-rule sanity, footprints net-checked.
- Trap: "same pinout" parts differ by temp grade.
$ netlist check
> missing C12 footprint
> temp grade -40..125C? OK
2
PCB layout 3–7 days
- Power rails first, then high-current, then signal.
- Decoupling within 2 mm of pins, via stitching return paths.
- Trap: auto-router passes DRC but fails EMC.
$ DRC sweep
> clearance 0.21mm OK
> decoupling 24/24 in range
3
Fab & assembly 5–10 days
- Panelize small boards, add fiducials, order 2–3 spares.
- JLCPCB: check base vs extended parts — extended doubles lead time.
- Trap: silkscreen over test pads hides probing points.
$ JLC cart
> base 11 parts OK
> extended 2 → swap!
4
Bring-up & debug 1–3 days
- Ramp power on a current-limited supply first, then USB.
- Fix document per revision: photo + diff + verdict.
- Trap: "works on bench" is not "works on battery sag".
$ bench
> 3.3V rail 3.28V OK
> sleep 18.2 uA OK